It's all happenning
It's all happening today. The fabricators have started erecting the portal house frame. The shed builders are covering the last wall. The concretors are forming up the upper path and observatory plinths. Glover is beavering away at the middle path with the little excavator. Even the guys from the council sewer department are at the bottom of the block working on the new sewer connection into the mains.
Here is the first columns of the house...
And the caps for the telescope mounts...
And the progress on the shed...
And the paths. The top one is being formed for a concrete pour next week. The middle one has been worked thoroughly to achieve the ideal slope and gradient. The paths were going to be goat tracks but they have morphed into generously proportioned paths. Not only will they give me and visitors easy access to the hanging gardens, but they will catch and divert surface stormwater away from the buildings.